Milestones

  • Building 1 - CBA 

    2017 Q1 Development works commence 
      Civil works commence
      Structural works commence 
     Q2 Public Domain works commence 
    Q3 Façade and internal finishes
    2019 Q2 Practical Completion 

     

    Building 2 - CBA 

    2017 Q1 Development works commence 
      Civil works commence
     Q3 Structural works commence 
     Public Domain works commence   
    2018 Q3 Façade and internal finishes 
    2020 Q2 Practical Completion 

     

    Building 3 - Community Building 

    2017 Q2 Development works commence 
     Q4 Structural works commence
    2018 Q1 Façade and internal finishes 
    2019 Q2 Practical Completion 

     

    *Please note the above information is indicative only and subject to change